It takes 6 workers 8 hours to tile a hall . How long will it take 4 workers to complete the same job

Respuesta :

icandoitjwk icandoitjwk
  • 15-01-2022
6w=8
2w=8/3

So
4w=8/3x2
4w=16/3
Answer Link

Otras preguntas

All the boxes in a certain warehouse were arranged in stacks of 12 boxes each, with no boxes left over. After 60 additional boxes arrived and no boxes were remo
Which wireless communication is typically limited to six feet of distance? Bluetooth IR NFC RFID
A small metal ball hangs from the ceiling by an insulating thread. The ball is attracted to a positively charged rod held nearthe ball. The charge of the ball m
How might a voracious, yet sporadic person behave?​
A student stumbles backward off a dock and lands in a small boat. The student isn’t hurt, but the boat drifts away from the dock with a velocity of 0.85 m/s to
Fungi hyphae have a structure that is most similar to the _____ of plants. ARoots incorrect answer BStems incorrect answer CLeaves incorrect answer DFlowers
y=2X+2, y=0 substitution ​
Calculate the molar solubility of silver chloride in 0.15 M sodium chloride. Ksp of silver chloride = 1.6x10-10.
The average annual weather conditions in a given location. Group of answer choices tundra equator tornado climate
help me asap need it