  • Mathematics
contestada

You work as a coordinator for data entry projects. On one project, the status shows that 15% of the work was completed in 6 days. If the work progresses at the same rate, how many more days will be required to complete the remainder of the project.

Respuesta :

v32daf v32daf
  • 14-07-2019

Answer: 36 more days

Step-by-step explanation:

it averages out to 2.5% per day

Answer Link

Otras preguntas

By the end of the nineteenth century, technology in the industrial setting (factories)
why is the 2008 presidential election called the facebook election?
what is the area of a triangle that has a height of 8 feet and a base length of 5 feet? 1.25 feet 3.20 feet 10 feet 20 feet
Population I stars are found in what area of the Milky Way
which part of speech is the underlined word? it's peaceful to sit among the trees. a. preposition b. adverb c. verb d. adjective (among)
Manufacturing equipment is related to products as road is related to
What is the property of 1×9 = 9
Which was not a result of industrialization? A. Changed the kinds of products Americans used. B. Decreased opportunities for entrepreneurs. C. Changed
find the area of a triangle with a base length of 6 units and a height of 7 units. 10 units 13 units 14 units 21 units
4x+4ab=5x-6ab solve for x